Naslov Model osiguranja kvalitete upravljanja projektima remonta rafinerijskih postrojenja : doktorska disertacija
Naslov (engleski) Quality assurance model in refinery plants turnaround project management : doctoral thesis
Autor Marko Fabić
Mentor Duško Pavletić (mentor)
Član povjerenstva Zoran Jurković (predsjednik povjerenstva)
Član povjerenstva Duško Pavletić (član povjerenstva)
Član povjerenstva Živko Kondić (član povjerenstva)
Ustanova koja je dodijelila akademski / stručni stupanj Sveučilište u Rijeci Tehnički fakultet Rijeka
Datum i država obrane 2017-06-12, Hrvatska
Znanstveno / umjetničko područje, polje i grana TEHNIČKE ZNANOSTI Strojarstvo
Univerzalna decimalna klasifikacija (UDC ) 66 - Kemijska tehnologija. Kemijska i srodne industrije
Sažetak Provođenje projekta remonta kao najznačajnijeg poduhvata održavanja putem projektnog
zadatka iznimno je složeno te nerijetko završava neuspjehom. Dostupna literatura u obliku
knjiga i znanstveno-stručnih radova temelji se najčešće na osobnim iskustvima autora te na
empirijskim podacima bez značajne znanstvene metodološke analize. Takvi podaci su vrlo
često subjektivni, značajni kao smjernice u istraživanju, ali znanstveno neutemeljeni. Jedan od
razloga nedostupnosti literature o projektima remonta je upravo složenost znanstvenog
područja koje objedinjava tematiku upravljanja održavanjem, kvalitetom i projektima.
Svrha i ciljevi ovoga rada su definiranje koncepta modela osiguranja kvalitete upravljanja
projektima remonta rafinerijskih postrojenja. Definiranje koncepta modela temelji se na šest
varijabli međusobno povezanih putem pet hipoteza. Svih pet hipoteza modela testirano je
logističkom regresijom. Dobiveni rezultati potvrdili su međuodnos varijabla te su sve hipoteze
potvrđene. Najznačajniji doprinos je definiranje uspješnosti za projekt remonta te definiranje i
implementacija varijable složenosti. Varijabla složenosti je od iznimnog značaja za uspješnost
projekta remonta. Analizom modela potvrđeno je da se povećanjem složenosti smanjuje
uspješnost. Na osnovi dobivenih rezultata zaključuje se da se povećanjem kvalitete pojedinih
elemenata modela povećava uspjeh upravljanja projektom, čime se u konačnici pozitivno
utječe na postizanje ciljeva, tj. uspješnost projekta remonta.
Nadalje, u sklopu ovog istraživanja provelo se djelomično testiranje postavljenog modela
osiguranja kvalitete upravljanja projektima remonta rafinerijskih postrojenja na projektu
remonta realiziranog tijekom 2013. godine u Rafineriji nafte Rijeka pod projektnim nazivom
TA-13. Analiza postavljenog modela izvršena je na osnovi deskriptivnih podataka. Analizom
je utvrđeno da deskriptivni podaci pružaju indikacije da bi postavljeni odnosi modela mogli
biti i statistički potvrđeni, pod uvjetom da je uzorak reprezentativan i dovoljno velik.
Sažetak (engleski) Implementation of the turnaround project, as the most significant maintenance project,
through the project task is extremely complex, and often ends in failure. Available literature
in the form of books, resesarch and professional papers are based mostly on personal
experiences and the empirical data without significant scientific methodological analysis.
Such data are subjective, significant as a guidelines in the study, but scientifically not
substantiated. One of the reasons of unavailability of the literature on turnaround projects is
the complexity of the scientific field that combines topics: maintenance management, quality
management and project management.
The purpose and objectives of this study are defining the concept of quality assurance model
of turnaround refinery plants project management. Defining the concept of the model is based
on the six interrelated variables connected through the five hypotheses. All five of the model
hypotheses were tested using logistic regression. The obtained results confirmed the
interrelationship between variables, and all hypotheses were verified. The most significant
contribution is defining the success for the turnaround project and definition and
implementation of the complexity variable. The variable complexity is of great importance for
the success of the turnaround project. The analysis of the model confirmed that the increase in
the complexity decreases the success. Based on the obtained results it is concluded that the
increase in the quality of individual elements of the model increases the success of project
management, which ultimately has a positive effect on the achievement of the objectives ie.
the success of the turnaround project.
Furthermore, as part of the research conducted testing of presented quality assurance model of
turnaround refinery plants project management.on the turnaround project realized during 2013
in Rijeka Refinery under the project name TA-13. Analysis of the presented model is
performed on the basis of descriptive data. The analysis shows that descriptive data provide
indication that the set model relations could be statistically confirmed, provided that the
sample is representative and large enough.
Ključne riječi
remont rafinerije nafte
upravljanje održavanjem
upravljanje kvalitetom
upravljanje projektima
složenost projekata
Ključne riječi (engleski)
refinery turnaround
maintenance management
quality management
project management
complexity of projects
Jezik hrvatski
URN:NBN urn:nbn:hr:190:214796
Datum promocije 2020
Studijski program Naziv: Poslijediplomski doktorski studij iz područja Tehničkih znanosti, polja Strojarstva, Brodogradnje i Temeljnih tehničkih znanosti i Interdisciplinarnih tehničkih znanosti Vrsta studija: sveučilišni Stupanj studija: poslijediplomski doktorski Akademski / stručni naziv: doktor/doktorica znanosti, područje tehničkih znanosti (dr. sc.)
Vrsta resursa Tekst
Opseg VII, 164 str ; 31 cm
Način izrade datoteke Izvorno digitalna
Prava pristupa Otvoreni pristup
Uvjeti korištenja
Datum i vrijeme pohrane 2020-11-24 08:45:17